Quick answer
Pass time t = (L + approach) / F, feed per minute F = f × RPM. Example: 4″ cut + 0.1″ approach at 0.008 IPR and 1000 RPM → F = 8 IPM, t = 4.1 / 8 ≈ 0.51 min ≈ 31 s per pass. Metric: 102 mm at 0.2 mm/rev, 1000 RPM — the same 31 s.
Result
- Time per pass
- —
- Passes
- —
- Cutting time per part
- —
- Part including handling
- —
- Whole batch
- —
Only feed moves are counted. Rapids, tool changes and spindle ramp-up add another 10–30 % — time the first part for an accurate figure. Facing with G96 (constant surface speed) is faster than at constant RPM.
Who needs it and why
- Quoting — job cost is based on machine time: how many hours the batch takes.
- Lead time — when the order will be ready and how many shifts the machine is busy.
- Choosing cutting data — what a higher feed or depth of cut buys you: how much faster the batch goes.
- Comparing stock — bar closer to the finished size means fewer passes and less time.
The formula
t = (L + approach) / (f × n) × passes, where f is feed per revolution and n is RPM. For facing L is half the diameter difference. Passes from stock are stock per side divided by depth of cut, rounded up.